10 years on the automation and technological
process optimization market.
Jaworzno – Power Plant Jaworzno III:
- 2007
- Analysis and optimization of neural network based burning process controller for boiler 3 – optimization packed NeuSight
Brzeg Dolny – Plastics Refinery
- 2006
- Design, delivery, commissioning and optimization of control system for prototype installation of transformation of plastics into hydrogen carbon fractions (DCS: FEELANCE, ABB);
Patnow – Power Plant Patnow
- 2007
- Optimization of close loop controls in scope of water steam cycle – new unit 464MW (ALSTOM technology)
Glinojeck – Sugar Mill Glinojeck
- 2007
- Design, programming, delivery, commissioning and optimization of control system for grate boilers K4, K5 and K6 (DCS: FREELANCE, ABB);